OpenAMRobot 2.0: where we are and what is next
- v2.0.0-rc.1 target: 20 November 2026 (pre-release). No 2.0 hardware is delivered and nothing is physically accepted. Two lines run in parallel: the legacy release-001 rig (H-day Mon 16 Nov confirmed: we plan to run the current 2.0 base software on the working v0.0.1 Teensy platform at 0.20 m/s, after the configuration and preflight checks, and publish the versions and results afterwards; Gate A check Fri 13 Nov and rehearsal Sun 15 Nov 18:00; a software test, not Build 1 commissioning or physical acceptance) and Build 1 (STM32 base controller, CAN, CTL-017 lift, bench week 23 to 27 Nov, integrated power-on 30 Nov to 4 Dec). Evidence on one line never counts for the other. v2.0.0 is 18 Dec.
- The critical path to rc.1: the stop gate platform-sw #90 (in review; the owner ruling of 8 Nov, D-13, D-14, D-34, is implemented; two human approvals at merge), the docking server platform-sw #125, StopState interfaces #35 and ui #50 (acceptance pins only after these merge, D-31); the electrical and firmware owner rulings due Wed 11 Nov (precharge, regen clamp, ZLAC8015D boot, brake gating, fuse blocks, W09: D-22 to D-25, D-28, D-33); and the Gazebo physics fault upperbody-sw #49: the simulated base and lift do not move while odometry reports motion, so simulation results that rely on odometry alone are not evidence until it is fixed.
- Design baseline: P-03 rev20.6 item 30 (8 Nov 2026, decisions D-01 to D-34), E-01 rev1.8, M-01 rev19.10, BOM Issue 7.15. Speed ceiling 0.5 m/s with a Category 0 stop (D-07); compute Jetson Orin NX 8 GB on the reComputer Robotics 104 (D-01). A revision number is not evidence: the safety chain is designed, not built.
This week: 6 to 9 Nov 2026
State at Mon 9 Nov 2026, 19:00 CET. Status words: merged (on main), pinned (in the rc.1 manifest), exercised in mock or simulation, hardware evidence. A decision does not make a thing implemented; a draft PR or a SIL result does not advance a hardware gate.
1. Decisions of 8 Nov 2026 (P-03 rev20.6 item 30)
- Thirty-four decisions D-01 to D-34 in nine rulings. Among them: Jetson Orin NX 8 GB on the Robotics 104 (D-01); receiver in a plastic frame, no metal within 20 mm of its sides, 15 mm above (D-02, D-03), charger bought later, build 1 charges manually (D-05); no cable or tie in the 214 to 232 mm slot band (D-06); Category 0 stop, 0.5 m/s ceiling, stop tests at 0.2, 0.3 and 0.5 m/s, stop limit 0.15 m (D-07); CTL-017 as one upper-body controller on CAN3 (D-11); the Resume rule (D-13, D-14) and the session-loss watchdog (D-15); lift fixing through the 260 x 30 mm foot tabs into the tapped MEC-019 (D-20) and the arch backing plate (D-21); two 4-cell battery trays (D-27); K1/K2 GX11CAC only (D-32).
- Six rulings stay with the electrical and firmware owner, due 11 Nov: precharge (D-22), regen clamp (D-23), ZLAC8015D boot configuration (D-24), brake gating and data (D-25), fuse blocks FB-A and F-CHG (D-28), W09 cable (D-33).
- The decisions register update is .github #90 (draft). Documents still to follow are listed on the Progress page (speed in older documents, brake role, BOM sheet text).
2. Software
- Merged: platform-sw #114 (maps volume) and platform-sw #115 (map_saver server) on 9 Nov; upperbody-sw #46 and #47 on 7 Nov; manifest #19 on 9 Nov.
- In review: platform-sw #90 (stop gate, head 60521c3), #125 (docking server), #91 and #92 (recovery behavior trees), #73 (SiteConfigStatus). Drafts: #129 (EKF on /imu/data_raw, D-10), #113 (stop-zone check, D-16), #126 (base masses from the roadmap export), upperbody-sw #48 (model and masses), #53 (simulated lift guard).
- Firmware: platform-fw main is the Teensy Gate A build only. The STM32 application, a CAN SIL with emulators and the CTL-017 lift firmware exist as draft PRs, not flashed, waiting for the owner rulings. Safety-path logic is written by the human owner only.
- UI: the rc.1 backend items wait on the integration branch ui #56; Stop also cancels navigate_through_poses (ui #60). The session-loss watchdog (D-15) is approved and not yet implemented.
3. Simulation evidence
- Gazebo physics fault upperbody-sw #49: in one run odometry reported 0.98 m while the simulated pose moved 0.006 m, and lift_joint stayed at 0 while the goal reported success. Every result that relied on odometry alone is marked affected on the Robot page. Retest: the simulated world pose and the lift joint state, not odometry. TF is unaffected. The 12 Nov stop-zone acceptance and the 13 Nov Gate A replay depend on the fix.
4. Hardware and procurement
- No 2.0 hardware delivered; procurement confirmation pending (two battery trays, D-27; K1/K2 contactors, D-32; compute after the inventory check).
- Chassis: the mechanical owner reruns the FEA with the double-shaft hub motor (700 N per wheel, 120 kg gross) and redesigns the sensor mounts; no chassis or cover change.
5. Roadmap model
- Owner decisions of 8 Nov in the model (docs #83, draft): mass ledger with every part counted once (robot 86.3 kg in docs #83; 87.1 kg with the BOM 7.15 arch backing plate and lift foot screws in this update: base 58.2 kg, static column 9.1 kg, carriage 6.7 kg; design values, not weighed), the slot rule on the cable outer surface, the lift fixing (D-20), the receiver frame (D-02, D-03) and the two lift cable openings. This update re-imports BOM Issue 7.15 and re-renders the stills, the exploded view and the tour videos; the store video and store pictures still show the model of 4 Nov.
Source: GitHub main and open PRs of each repository, P-03 rev20.6, E-01 rev1.8, M-01 rev19.10, BOM Issue 7.15, Build 1 software-to-hardware plan rev2 · 9 Nov 2026
OpenAMRobot 2.0: open-source mobile base with a 350 mm lift and two OpenArm 2.0 arms. Explore the 3D model, or get the robot model (URDF, MoveIt, Gazebo) on GitHub.
A. Where we are
What this shows: every part of the 2.0 system with its delivery status, runtime evidence and physical acceptance, and a one-line state.
How to read it: each box has a coloured left bar, a status chip with an icon and the status in words; rounded pills are runtime evidence, pointed boxes are physical acceptance; the legend buttons highlight every item with that status; a red triangle marks the critical path to rc.1, two rings mark the base design shared with release 001; select a block to open its detail.
Source: this roadmap's progress, robot, hardware and architecture pages (each block links to its evidence); GitHub state and audit pass 2 · 9 Nov 2026
B. What is next
What this shows: the work per area from today to v2.0.0 on 18 Dec, with the milestones and the dependencies between items.
How to read it: time runs left to right; solid bars and solid milestone lines are confirmed dates and name their source (P-02 rev19.2, the register, P-03 or an issue body), dashed bars are proposed targets from audit pass 2; items with no date in any source start today and end open (double chevron); a red triangle and red outline mark the critical path to rc.1, and dotted red arrows show which items feed rc.1; each box has a coloured left bar, a status chip with an icon and the status in words.
Scroll sideways inside the diagram.
Source: P-02 rev19.2 (Gate A and electrical/safety release 30 Oct, I8 freeze and STM32 go/no-go 6 Nov, Gate B 13 to 20 Nov), P-03 rev20.2 (Gate A full run 6 Nov; 30 Oct was Gate A partial, A1 control only), the decisions register (rc.1 20 Nov, v2.0.0 18 Dec), P-03 rev19.7 item 12 (integration window 23 Nov to 18 Dec), issue bodies for issue due dates (no repository uses GitHub milestones), audit pass 2 top 20 actions (proposed dates) · 9 Nov 2026
C. One base, two robots
What this shows: the base electrical design that release 001 and 2.0 are to share (recorded in the register and P-03 rev19.7 item 23, not built), and the intended controller and sensor differences.
How to read it: the centre box is the shared core (recorded, not built); each row says whether test evidence from release 001 carries over to 2.0; the side boxes are the intended differences. Details and the equivalence table are on the hardware page.
Shared core per E-01 rev1.6 (1 Nov) and B-02 rev18.10: battery of 8 x EVE LF105 with a Daly 8S 150 A BMS; F0 110 A Class T and the lockable disconnect BS-6004B on the BAT bus; two dual-channel E-stops in series into a Pilz PNOZ s3, which drives K1 and K2 in series (decision 2 Nov: Gigavac GX11CAC or a Schneider TeSys D LC1D80BD / Siemens 3RT2 size S3 with mirror contacts); precharge relay, resistor and 1 A fuse across K2 only; SAFE 24 V from a MEAN WELL DDR-240B-24 behind F-LIFT 15 A for the brake release and the lift; one ZLAC8015D for both hub motors on CAN1, the Daly BMS on CAN2 through the CTL-014 isolator, the upper-body controller CTL-017 on CAN3 (node 0x10, D-11); WCM-500-24 wireless charging plus manual charging through an Anderson SB50. The base controller of 2.0 is the NUCLEO-H723ZG with no click shield; the IMU is the TDK EV_ICM-42688-P on SPI4. Release 001 keeps its Teensy 4.0 until the STM32 go/no-go on 6 Nov.
Source: project-lead decision of 19 Oct 2026 by @BotshareAI (project lead), recorded in P-03 rev19.7 item 23 (20 Oct) and decisions.yaml SHARED-BASE (.github #55, 1c3f516); WCM-500-24 on both robots added 20 Oct; equivalence table on the hardware page · 9 Nov 2026
D. What to do next
The 10 most urgent of 38 steps of the proposed sequence, critical path first. Full action plan.
- 1. Decide K1/K2 on Mon 2 Nov 2026 under the availability rule: option A Gigavac GX11CAC, or option B Schneider TeSys D LC1D80BD / Siemens 3RT2 size S3 with mirror contacts. BUY-32 stays blocked until then. (step 2) critical path
@evans-kwashie (electrical, safety, firmware) · BLOCKED · due 2 Nov 2026 K1/K2 decision under the availability rule (P-03 rev20.2) - 2. Deliver the procurement buy lists under the availability rule (in stock at two or more independent suppliers). (step 36) critical path
owner: to be assigned; decisions @BotshareAI (project lead) · IN PROGRESS · due 2 Nov 2026 confirmed (procurement plan) - 3. Pass Gate A on the Jetson with the existing Teensy and drivetrain. (step 7) critical path
@evans-kwashie (electrical, safety, firmware) · MERGED UNTESTED · due 6 Nov 2026 confirmed (Gate A full run, P-03 rev20.2; 30 Oct was Gate A partial: A1 control only) - 4. Route UI teleop, blocks and voice actions into an arbitrated twist_mux input; the browser never publishes /cmd_vel. (step 10) critical path
@parthkeshari (UI lead) · IN REVIEW · due 6 Nov 2026 proposed (audit pass 2 action 1) - 5. Define the twist_mux input topics, priorities and timeouts for #35 option (b) in a contract change request. (step 6) critical path
@skunal3318 (navigation) · IN REVIEW · due 30 Oct 2026 confirmed (platform-sw #35 issue body) - 6. Decide which base controller rc.1 runs (historical; settled 9 Nov: Teensy for the 16 Nov software test, STM32 for Build 1). (step 15) critical path
to be confirmed · NOT STARTED · due 6 Nov 2026 confirmed (P-02 rev19.2 STM32 go/no-go; fallback Teensy; historical; settled 9 Nov: Teensy for the 16 Nov software test, STM32 for Build 1) - 7. Freeze the I8 base-controller contract. (step 16)
@evans-kwashie (electrical, safety, firmware) · DOCUMENTED ONLY · due 6 Nov 2026 confirmed (P-02 rev19.2, I8 freeze) - 8. Confirm the absolute positions of the Getac, head light, second E-stop and lift stop sensors (work package M-09) and push the CAD fixes promised on 31 Oct. (step 37) critical path
@fridayali (mechanical CAD, URDF, docking) · NOT STARTED · due none in any source - 9. Deliver the BMS and power distribution layout with real part sizes for the rear battery zone. (step 38) critical path
@evans-kwashie (electrical, safety, firmware); tray MEC-007 @fridayali (mechanical CAD, URDF, docking) · NOT STARTED · due none in any source - 10. Land #35 option (b): docking commands through the chain without switching the collision monitor off. (step 11) critical path
@skunal3318 (navigation); @fridayali (mechanical CAD, URDF, docking) · IN PROGRESS · due 30 Oct 2026 confirmed (platform-sw #35 issue body); audit pass 2 action 2 proposed 6 Nov
How to read this
- Delivery status, runtime evidence and physical acceptance are separate. Simulation, fixtures and mock hardware are development evidence, not acceptance.
- critical path to rc.1 · shared with release 001 · dashed outline: proposed target or no date set.
- People are shown by GitHub handle and role.